AL HAZAA’ PV PROJ ECT 16.4 MW

Project Details
1

The project work was to design, build, operate and maintain a 1 6.4 MW Solar Plant in Amman – Al Zumailah for Al Hazaa’ for Renewable Energy Co.

Works included the following:

  • All the engineering civil, electrical & mechanical works.
  • 27 underground MV cable from the location of the project to (QAIA) Queen Alia International Airport substation.

Design, Build, Operate, maintain and transfer a 3.3MW Solar Plant at Al Hussein Bin Talal University (DPOT).

Work included the following:

  • All the Civil, Electrical & Mechanical works.
  • Connection to the local grid.
  • MV work (three transformers and 11KVA Delivery station).

Design, build, operate, and maintain a 300KW Solar system at the steel Hunger of the MS Pharma factory at Sahab area.

Works include the following:

  • All the load analysis studies for the existing hunger.
  • Civil, electrical & mechanical works.
  • Connection to the local grid.

Design, Build, Operate and maintain 350KW Solar system at the Mayar International School.

Project scope included the following:

  • Design and build the car parking canopies and foundations that were used for PV cells installation.
  • Civil, electrical & mechanical works.
  • Connection to the local grid.